Grenada National Resort Construction Update – November 2025

November saw steady progress across the Grenada National Resort, with significant milestones achieved across the hotel complex, golf course, and supporting infrastructure.

Hotel Tower 1 advanced to its 14th floor, while the hotel lobby’s main structure reached full completion, marking a key milestone for the resort’s central welcome experience.

Construction at the future casino continues to gain momentum, with additional sections of the first-floor suspended slab successfully poured. On the 18-hole championship golf course, earthwork balancing and rough shaping progressed across multiple fairways, complemented by extensive stone-retaining-wall works along water-system slopes.

Our on-site production facility remained in full operation throughout the month, providing a steady supply of high-quality concrete bricks and precast drainage pipes to support ongoing construction.

Each development brings the Grenada National Resort closer to reality, reaffirming our commitment to delivering a world-class destination for visitors and the local community.